Project Phase

Project Summary

In the 2019 Bond election, voters approved Project No. 63 to provide additional parking facilities in Old Town. On July 1, 2024, Council gave direction to proceed with the addition of two levels to the existing City-owned parking structure at 1st Street and Brown Avenue.

Project Information

Budget: $20,900,000

Sponsoring Division: Tourism & Events

Funding Source: Bonded

Project Location: First St. and Brown Ave.

Contact Information

Roger Berna
Project Manager
480-312-7845
Roger Berna

On Feb. 11, 2025, the City Council approved a Design Build Manager of Chasse Building Team to design the garage.  Design work will take place for the rest of 2025 and construction is tentatively scheduled to begin in the summer of 2026.

Project Status

The project team is currently in the data collection phase and will be conducting survey work at the current structure. The project team will meet with the community to go over site conditions and explore design options early in the design process.

Community Outreach

Join us for a public meeting to kick off the design process on the Brown Avenue Parking Structure at 8:30 a.m. on Thursday, May 22, at the Civic Center Library Auditorium, 3839 N. Drinkwater Ave., Scottsdale. Meet the project team, learn more about the process they will follow to design two additional levels of parking for the existing structure and share elements of what you would like to see in the upgraded parking structure.

The Old Town Farmers Market

The Old Town Farmers Market is currently held at this location – and will continue here through the 2025/2026 season, when construction preparations on the site are expected to begin.

The city is working with the Old Town Farmer’s Market to identify an alternative location in Old Town where they can continue to operate after this project begins.

Project Schedule

February 2025Design Contract Approved by City Council and Design Work Begins
Spring 2025Public Meeting #1
Late Summer/Early Fall 2025Public Meeting #2
Fall 2025Design Review Board
Summer 2026Construction Begins
Spring 2027Construction Complete

Project History

In 2017 the city commissioned a study of the existing structure and the feasibility to add additional levels to the parking structure. Currently the structure is designed to accommodate up to three additional levels.

The study confirmed that the existing structure, originally constructed in 2004, was in good condition and capable of supporting additional floors. It recommended two options: Option 1, add three levels and eliminate the east/west alley access, or Option 2, add two levels with an elevated second level allowing east/west access for high profile vehicles.

At the April 16, 2024, City Council Work Study session, staff presented the expansion of the 1st Street and Brown Avenue parking structure along with two other options to expand parking in the most needed areas of Old Town. City Council directed staff to move forward with building two structures. Within available bond funding, the city will construct two additional levels at the 1st Street and Brown Avenue parking structure and under separate appropriation, an additional structure will be built in the Northeast quadrant of Old Town.

Back to Top