Due to the extent of the work required, aircraft parking and operations will be limited throughout the duration of the project. Arrival and departures may be relocated to Signature Flight Support's facility on the west side of the runway. The project will be done in four phases (see below) to minimize the impact on customer and tenant operations.

Sig phase map 

Phase 1

Phase 2

Phase 3

Phase 4

 

Project phasing:

Phase 1 (May 1  - June 1): This phase will require the closure of a large section of the ramp along the main terminal building. No vehicle traffic or parking will be permitted in this area during this phase. 
 
Phase 2 (June 1 - July 1): This phase includes removing and replacing concrete along the south entrance of their ramp exciting from Taxiway "B". During this phase, all aircraft will need to arrive and depart via the north entrance. This will result in arrival and departure delays.
 
Phase 3 (July 1 - August 1): During this phase, access to the Alpha Hangar will be limited. 
 
Phase 4 (August - September): The north arrival and departure ramp entrances will be closed. Aircraft will access the ramp via the south entrance off of Taxiway "B."
 
For more information on this project, please contact Signature Flight Support at 480-951-2525.

Subscribe to Scottsdale Update

 

Get the latest Scottsdale news & events in your inbox each week -- just enter your email above.

The Scottsdale Update printed newsletter is included in utility bills six times each year. Download recent issues below (PDF)

Scottsdale Video Network

Need Help?

480-312-3111

General City Information/Speak to a Citizen Service Specialist


Stay Up To Date

Manage Newsletter Subscriptions
(Subscribe / Unsubscribe)