Search Home

Scottsdale traffic restrictions July 21 - 30

The following is a partial list of road construction projects and traffic restrictions taking place in Scottsdale July 21 - 30. For more information, contact Traffic Engineering at 480-312-7250.

Get the latest information on traffic conditions and accidents by following us on Twitter @DriveScottsdalelinks to external site.

Hayden Road restricted for gas line installation

Southbound Hayden Road will be reduced to one lane from Indian School Road to Thomas Road through September 30 while a new gas pipeline is installed. For more information, please see the Southwest Gas flyer or call the construction hotline at 602-750-7139links to external site

Water line installation underway on Frank Lloyd Wright Boulevard

Lane restrictions began May 30 on Frank Lloyd Wright Boulevard from Via Linda to 90th Street so a new water line can be installed. Construction will take place in the westbound lanes of Frank Lloyd Wright Boulevard, and all traffic will be diverted to the eastbound lanes as necessary. Construction is expected to be complete by the end of the year. The following are more specific lane restrictions occurring on Frank Lloyd Wright Boulevard May 30 - July 31 for water line construction:

  • Traffic on Frank Lloyd Wright Boulevard will be reduced to one lane in each direction from Via Linda to Thunderbird Road except northbound Frank Lloyd Wright boulevard will have two lanes open north of 101st Way to immediately south of Thunderbird Road July 26 - 31. 
  • Left turns in both directions on Frank Lloyd Wright Boulevard will be closed at Thunderbird Road/Gray Road. 
  • All left turns at the intersection of Frank Lloyd Wright Boulevard and 100th Street will be restricted. 
  • Traffic on 100th Street will be reduced to one lane in each direction at Frank Lloyd Wright Boulevard. 
  •  Northbound traffic on Frank Lloyd Wright Boulevard will be reduced to one lane and the southbound left turn only lane will be closed at Raintree Drive July 24 - 28. During those same dates traffic in both directions on Raintree Drive will be reduced to one lane and no left turns will be permitted at Frank Lloyd Wright Boulevard. 
  • Traffic will be reduced to one lane in both directions on Frank Lloyd Wright Boulevard at 101st Way July 21 - 26. During those same dates, no left turns will be permitted at 101st Way for southbound traffic on Frank Lloyd Wright Boulevard. Use 100th Street as a detour. 
  • Eastbound Redfield Road will be reduced to one lane immediately west of Frank Lloyd Wright Boulevard July 22 - 28. No left turns will be permitted from eastbound Redfield Road onto Frank Lloyd Wright Boulevard.
  • During those same dates No left turns will be permitted on Frank Lloyd Wright Boulevard at 101st Way July 26 - 31.

For more information or to sign up for updates from Scottsdale Water, visit the project website or at ScottsdaleAZ.gov, search “FLW water line.”

ROAD RESTRICTIONS SOUTH OF INDIAN BEND ROAD 

  • The westbound curb lane on Indian School Road will be closed from Miller Road to Drinkwater Boulevard 9 a.m. to 3:30 p.m. Friday, July 21, for utility work. During the same date and times, the southbound curb lane on Miller Road will be closed immediately south of Indian School Road. 
  • 82nd Street will be closed from Thomas Road to Oak Street 6 a.m. to 4:30 p.m. July 24 - 28 for paving. During those same dates and times Oak Street will be closed from Granite Reef Road to Hayden Road. 
  • Southbound Hayden Road will be reduced to one lane from Osborn Road to Thomas Road July 20 - Sept. 12 for trench work. During those same dates, northbound Hayden Road will be reduced to one lane at Thomas and Indian School roads.
  • Northbound Marshall Way will be closed from north of Second Street to First Street July 19 - Aug. 25 for sidewalk and roadway improvements. Detour on Main or Second streets to Goldwater Boulevard.
  • Southbound 64th Street will be reduced to one lane immediately south of Thomas Road 8:30 a.m. to 3:30 p.m. weekdays July 21 - 28 for utility work. 
  • Multiple lane restrictions will occur on Thomas Road between 57th Place and 61st Place 8:30 a.m. to 4 p.m. Monday through Saturday, July 17 - 31, for utility work. 
  • The eastbound curb lane on Indian School Road will be closed from 68th Street to Scottsdale Road 8:30 a.m. to 4 p.m. July 18 - 21 for ADA ramp construction. 
  • The following restrictions will occur near the intersection of Scottsdale and Osborn roads 9 p.m. to 6 a.m. weeknights July 9 - 23 for utility work:
    • Northbound Scottsdale Road will be reduced to one lane from immediately north of Earll Drive to Osborn Road.
    • Southbound Scottsdale Road will be reduced to one lane from immediately north of Osborn Road to Angus Drive.
    • Southbound Scottsdale Road will be reduced to one lane from immediately north of Osborn Road to Angus Drive. 
  • Southbound traffic on Miller Road will be shifted to the two-way left-turn lane from McKellips Street to Diamond Street 6 a.m. to 4 p.m. July 17 - 21 for road work. During those same dates, the following restrictions will also be in place from 8:30 a.m. to 4 p.m.:
    • The northbound left turn lane and the westbound curb lane will be closed at the intersection of Miller Road and McKellips Street.
    • No left turns will be permitted on Miller Road at McKellips Street. 
  • The following restrictions will occur near Camelback Road and Goldwater Boulevard 8:30 a.m. to 3:30 p.m. weekdays July 5 - 21 for utility work:
    • The westbound curb lane on Camelback Road will be closed from Scottsdale Road to Goldwater Boulevard.
    • The southbound right turn bay on Scottsdale Road will be closed at Camelback Road.
    • The northbound curb lane on Goldwater Boulevard will be closed from Via Soleri Drive to Camelback Road. 
  • Westbound Indian School Road will be reduced to one lane from 82nd Street to immediately west of 81st Street July 5 - Aug. 1 for utility work.
  • Eastbound Indian School Road will be reduced to one lane from Hayden Road to 81st Street 8:30 a.m. to 3:30 p.m. July 5 - Aug. 1 for utility work. 
  • 86th Street will be reduced to one lane at McDonald Drive 8:30 a.m. to 4 p.m. weekdays July 10 - 28 for utility work. Flaggers will control traffic on 86th street from Hazelwood Street to Montebello Avenue. 
  • Northbound Marshall Way will be closed north of Goldwater Boulevard to Second Street June 13 - Aug. 25 for sidewalk and roadway improvements. Detour on Goldwater Boulevard to Second Street or Bishop Lane. During those same dates, the westbound curb lane on Goldwater Boulevard will also be closed. 
  • Southbound Hayden Road will be reduced to one lane from Indian School Road to Thomas Road May 31 - Sept. 30 for utility work.
  • The westbound curb lane on McDowell Road will be closed from Miller Road to Scottsdale Road May 3 - Sept. 3 for sidewalk improvements. During those same dates the southbound right turn lane on Miller Road will be restricted at McDowell Road, and northbound traffic on 74th street will be shifted to the left turn lane at McDowell Road. 
  • Westbound Main Street will be closed 24 hours from McKnight Avenue to 75th Street through Sept. 7 for condo construction. Detour on McKnight Avenue. 

ROAD RESTRICTIONS FROM INDIAN BEND TO THUNDERBIRD ROADS

  • The southbound right turn bay on Pima Road will be closed at Indian Bend Drive 6 a.m. to 3:30 p.m. Friday, July 21, for ADA ramp work.
  • The northbound curb lane on Scottsdale Road will be closed immediately south of Mountain View Road 8:30 a.m. to 3:30 p.m. weekdays July 18 - Aug. 1 for boring.
  • Southbound 94th Street will be reduced to one lane from Sweetwater Avenue to Larkspur Drive 8:30 a.m. to 4 p.m. July 26 - 27 for road work. From 7 a.m. to 4 p.m. ln those same dates, flaggers will direct traffic on Larkspur Drive. 
  • Curb lanes in both directions on 96th Street will be closed immediately north of Shea Boulevard 8:30 a.m. to 4 p.m. Monday through Saturday, July 13 - 27, for utility work. 
  • The westbound curb lane on Shea Boulevard will be close from Scottsdale Road to 70th Street 8:30 a.m. to 3:30 p.m. weekdays July 13 - 27 for utility work. During those same dates, restrictions will occur in both directions on Shea Boulevard at the intersection of Scottsdale Road 10 p.m. to 6 a.m. 
  • Southbound 124th Street will be reduced to one lane at Sahuaro Drive 7 a.m. to 4 p.m. Monday through Saturday, July 10 - 24, for boring and potholing. 
  • The eastbound median lane on Shea Boulevard will be closed at 124th Street 6 a.m. to 2 p.m. July 11 - 31 for median work. 
  • Bike lanes in both directions on 104th Street will be closed at Charter Oak Drive 8:30 a.m. to 4 p.m. Monday through Saturday, July 5 - 21, for utility work.
  • Lane restrictions will occur in both directions on Lakeview Drive at 103rd Street 8:30 a.m. to 4 p.m. weekdays June 19 - 30 for boring.
  • 90th Street will be reduced to one lane in both directions between Shea Boulevard and Mountain View Road April 6 - July 31 while the median is removed. 

ROAD RESTRICTIONS NORTH OF THUNDERBIRD ROAD 

  • The northbound curb lane on Northsight Boulevard will be closed from immediately north of 87th Street 8:30 a.m. to 4 p.m. Monday through Saturday, July 18 - 28, for trench work. During those same dates and times, the northbound curb lane on 87th Street will be closed immediately east of Northsight Boulevard. 
  • Westbound traffic on Bahia Drive will be shifted to the center two-way left-turn lane from immediately east of 91st Street to immediately west of 90th Street weekdays July 18 - 25 for utility work. 
  • Thompson Peak Parkway will be reduced to one lane in each direction from 87th Street to Desert Camp Drive 6 a.m. to 6 p.m. July 27 - Aug. 2 and Aug. 4 - 7 for road work. 
  • The center left turn lane on Bahia Drive will be closed between 90th and 91st streets 8 p.m. to 5 a.m. weeknights, July 17 - 28, for utility work.
  • The southbound curb lane on 100th Street will be closed at Raintree Drive 8:30 a.m. to 4 p.m. weekdays July 14 - 28 for trench work. During those same dates and times, traffic in both directions will be shifted to the south side of Raintree Drive at 100th Street. 
  • The westbound curb lane on Ashler Hills Drive will be closed at Scottsdale Road 8:30 a.m. to 3:30 p.m. July 17 - 28 for utility work. 
  • Traffic in both directions on 74th Street/Los Portones Drive will be shifted to the east side of the road 8:30 a.m. to 4 p.m. Monday through Saturday, July 17 - 31, to permit utility work on the west side of the road. 
  • Bike lanes in both directions on Jomax Road will be closed at Hayden Road 7 a.m. to 4 p.m. weekdays July 13 - 21 for utility work. 
  • Traffic in both directions on Los Gatos Drive will be controlled by a flagger immediately east of Pima Road 7 a.m. to 4 p.m. weekdays July 12 - 21 for utility work.
  • Southbound traffic on 118th Street will be shifted toward center of road at Buckskin Trail July 11 -28 while a storm drain is installed. 
  • Scottsdale Road will be reduced to one lane in both directions from Jomax Road to Pinnacle Peak Road 6 a.m. to 6 p.m. July 20 - 25 and Aug. 2 - 4 for road work. 
  • Scottsdale Road will be reduced to one lane in both directions from Carefree Highway to Westland Road 6 a.m. to 6 p.m. July 20 - 25 and July 31 - Aug. 1 for road work. 

Subscribe to Traffic Restrictions