Date |
Event |
Description |
Prior to February 29 |
Preliminary Consultation |
Discussion with Planning staff regarding whether a proposal qualifies as a Major General Plan Amendment. |
| February 29th - April 24 |
Applicant pre-submittal preparation |
Applicant begins Neighborhood Involvement, post “Project Under Consideration” sign, holds Open House meeting(s), and prepares for application submittal. |
| April 24 |
Application Submittal Deadline* |
All Major General Plan Amendment applications must be received by this date to be processed in the 2008 review cycle. |
| May 22 |
Companion Case Submittal Deadline |
Submittal of companion zoning case shall occur on or prior to this date. |
| May 28 |
Planning Commission Study Session |
Study Session to provide an overview of the 2008 applications to the Planning Commission. No public comment will be taken at this time. |
| June 2 |
Open House |
City-hosted community open house |
| Aug 27 |
Planning Commission |
Remote Planning Commission hearing on Major General Plan requests |
| Sept 24 |
Planning Commission |
Regular Planning Commission hearing on Major General Plan requests (5 p.m., City Hall Kiva) |
Tentative: Oct. 27th, 28th, 29th, 30th & 31st |
City Council |
City Council hearing on Major General Plan requests (5 p.m., City Hall Kiva) |