Permits are required when:
Building any fence over 3-feet in height. No permit required for constructing Wall/Fence which is less than 3' in height. (Site plan approval will verify setbacks and property lines).
- Adding additional height to existing fences over 3-feet in height. Engineered plans may be required when adding height to existing fences.
- Constructing a retaining wall. All retaining walls require engineered plans to be submitted and approved by the City.
- Building keystone or keystone-type walls over 30-inches in height.
- Replacing an existing fence. The same requirements apply when replacing an existing fence as apply when building a new fence.
REPAIRING A FENCE?
Before removing the fence, check with the One Stop Shop on-call planner to make sure the fence is not non-conforming. Non-conforming fences that are removed cannot be replaced in the same, non-conforming location and will be required to meet current zoning specifications related to placement, height, etc.
No permit is required if minor repairs to the fence are NOT changing LOCATION...HEIGHT...or MATERIALS. |
Keeping you informed
R1-7 Fences & Walls Text Amendment (1-TA-2007) Tentatively scheduled for Oct 19th Planning Commission Hearing
Key Resources
The review time for walls/fences is 15 calendar days.
|