Project Schedule

 

 

RFQ for Construction Manager at Risk

July 2012

Council Approval of Construction Contract

September 11, 2012

Dry Utility Relocations  Sept. 2012 – Jan. 2013
Pinnacle Peak Intersection Improvements  October 2012
Water & Sewer Relocations

Oct. – Nov. 2012

Bridge

Dec. 2012 – Oct. 2013

Public Art October 2013
Pavement Overlay* Oct./Nov. 2013
Construction Complete November 2013

*Additional details will be provided as they become available.

 

For additional information please see the Construction Sequence Map.