Parks, Recreation and Senior Services - 14 Projects - $112.6M
CIP Project No. | CIP Project Title | Estimated Budget | Running Total |
---|---|---|---|
2 | Add Splash Pad and Improve Walkways at McCormick-Stillman Railroad Park | 917,207 | 917,207 |
10 | Replace Tennis Court Surface at Indian School Park and Scottsdale Tennis Center | 3,497,104 | 4,414,311 |
13 | Expand Granite Reef Senior Center to Meet Demand for Adult Day Care Center | 2,972,175 | 7,386,486 |
21 | Expand Via Linda Senior Center to Meet Demand for Senior Services | 4,538,632 | 11,925,118 |
22 | Build New Swimming Pools and Replace Building at Cactus Pool | 31,229,600 | 43,154,718 |
24 | Install High Efficiency Sports Lighting at 4 Facilities | 1,224,304 | 44,379,022 |
25 | Replace Aging Buildings that Comprise Paiute Community Center | 11,174,242 | 55,553,264 |
30 | Indian School Park Field 1 Lighting | 696,072 | 56,249,336 |
41 | Install Solar Heating System for Eldorado Pool | 560,332 | 56,809,668 |
42 | Add a Dog Park to Thompson Peak Park | 4,637,357 | 61,447,025 |
53 | Build Multi-Use Sport Fields in the area of Bell Road | 40,000,000 | 101,447,025 |
55 | Build a 17-Acre Neighborhood Park at Ashler Hills Drive and 74th Way (Whisper Rock) | 6,097,659 | 107,544,684 |
60 | Double the Solar Power Generating Capacity at Appaloosa Library | 39,688 | 107,584,372 |
61 | Purchase land, expand Pinnacle Peak Park parking lot, staff office and restrooms, renovate hiking trail and construct an interpretive trail | 5,000,000 | 112,584,372 |
Total | 112,600,000 |
Community Spaces and Infrastructure - 20 Projects - $112.3M
CIP Project No. | CIP Project Title | Estimated Budget | Running Total |
---|---|---|---|
1 | Replace Aging Infrastructure and Improve Public and Event Spaces on Civic Center Plaza | 27,317,840 | 27,317,840 |
15 | Build 200 Space Parking Lot off 75th Street to Serve the City Court and Scottsdale Stadium | 1,530,709 | 28,848,549 |
18 | Build Roadway and Pedestrian Improvements along 2nd Street from Drinkwater Blvd to Goldwater Blvd | 1,845,427 | 30,693,976 |
19 | Build Roadway and Pedestrian Improvements along Marshall Way North of Indian School Road | 1,800,780 | 32,494,756 |
20 | Build Roadway and Pedestrian Improvements along Main Street from Scottsdale Road to Brown Avenue | 994,180 | 33,488,936 |
23 | Repair Lakes and Irrigation at Vista del Camino Park in the Indian Bend Wash | 23,512,804 | 57,001,740 |
32 | Renovate and Modernize the Stage 2 Theater at the Scottsdale Center for the Performing Arts | 1,200,000 | 58,201,740 |
43 | Improve 5th Avenue from Scottsdale Road to Goldwater Boulevard | 3,569,857 | 61,771,597 |
45 | Renovate WestWorld Horse Barns to Increase Rentable Space | 4,702,972 | 66,474,569 |
46 | Replace the Public Address System at WestWorld | 366,132 | 66,840,701 |
47 | Replace WestWorld Arena Lights to Reduce Operating Costs | 1,331,273 | 68,171,974 |
48 | Widen 94th Street at WestWorld to Improve Access | 1,469,153 | 69,641,127 |
50 | Renovate Arena at WestWorld to Provide Flexible Event Space | 960,298 | 70,601,425 |
51 | Install Permanent Lighting at WestWorld Parking Lots to Reduce Operating Costs | 1,438,293 | 72,039,718 |
52 | Expand Restrooms in WestWorld North Hall | 701,532 | 72,741,250 |
57 | Install Solar Systems North Corporation Campus | 4,810,300 | 77,551,550 |
58 | Install Parasol Solar Shade Structure at City Hall Parking Lot | 4,669,400 | 82,220,950 |
59 | Install Solar Systems at Civic Center Campus | 2,784,500 | 85,005,450 |
62 | Build a Bridge on Thompson Peak Parkway Bridge over Reata Pass Wash to Improve Safety | 6,300,000 | 91,305,450 |
63 | Build Parking Structures in Old Town Scottsdale | 20,962,800 | 112,268,250 |
Total | 112,300,000 |
Public Safety and Technology - 24 Projects - $94.1M
CIP Project No. | CIP Project Title | Estimated Budget | Running Total |
---|---|---|---|
4 | Replace Outdated Emergency Response Equipment for Fire Department | 2,057,000 | 2,057,000 |
5 | Modernize Computer Equipment Rooms to Protect City Servers | 691,600 | 2,748,600 |
6 | Replace Emergency Power Source for Public Safety Radio Network | 305,240 | 3,053,840 |
7 | Replace Outdated 9-1-1 Computer Aided Dispatch and Records Management to Improve Efficiency | 591,156 | 3,644,996 |
8 | Replace Website Management Software | 188,556 | 3,833,552 |
9 | Install Fiber Optic Infrastructure to Reduce Operating Costs | 11,385,555 | 15,219,107 |
11 | Replace Document Management System to Improve Public Access to Information | 674,000 | 15,893,107 |
12 | Update Scottsdale's 15-year-old Digital Terrain Model | 177,240 | 16,070,347 |
14 | Replace Obsolete Planning and Permitting Software | 2,964,000 | 19,034,347 |
16 | Replace the City's Obsolete Training Software | 342,000 | 19,376,347 |
17 | Obtain a Citywide Data Management and Analytics Solution for Data-Based Decision Making | 62,000 | 19,438,347 |
26 | Replace Deteriorating Vehicle Training Track at the Police and Fire Training Facility | 1,919,401 | 21,357,748 |
27 | Modernize and Expand the Police and Fire Training Facility | 4,227,262 | 25,585,010 |
28 | Build a New Fire Station near Hayden Road and the Loop 101 to Improve Response Times | 10,470,043 | 36,055,053 |
29 | Replace Workstations at 911 Communications Dispatch Center to Accommodate New Technology | 638,522 | 36,693,575 |
33 | Renovate the Via Linda Police Station to Increase Efficiency | 16,600,000 | 53,293,575 |
34 | Build New Fire Station at 90th Street and Via Linda to Replace Aging Facility | 5,914,028 | 59,207,603 |
35 | Install Bullet Proof Glass in Reception Areas of Police Department Facilities | 977,256 | 60,184,859 |
36 | Provide Free Public WiFi at the Civic Center Plaza | 57,200 | 60,242,059 |
37 | Implement an Inventory and Asset Control System for City Technology | 572,000 | 60,814,059 |
38 | Build a new Fire Department Training Facility | 18,258,520 | 79,072,579 |
39 | Renovate the Foothills Police Station to Accommodate Current Staffing Levels | 1,024,000 | 80,096,579 |
40 | Renovate and Expand the Civic Center Jail and Downtown Police Facility to Meet Demand | 13,102,518 | 93,199,097 |
44 | Replacement of Fire Utility Truck to be used on fire ground activity and response to Hazardous Materials and Technical Rescue incidents | 782,638 | 93,981,735 |
Total | 94,100,000 |